Survey Development Timetables
From EvaluationWiki
Timetable for Major Surveys[1]
(Calendar Day in parentheses)
- Deliver to printer (1)
- Printing completed (14)
- Receipt of questionnaire by local surveying activities (24)
- Receipt of survey questionnaires by respondents (30)
- Six-week administration period ends (75)
- Answer sheets or completed questionnaires returnedby respondents (80)
- Receive completed answer sheets by data reductionactivity (90)
- Initial results available (100)
Timetable for Surveys With Expedited Printing and Direct Mailing to Respondents[1]
(Calendar Day in parentheses)
- Printing completed (1)
- Receipt of survey questionnaires by respondents (17)
- First of questionnaires returned to surveyor (27)
- Follow-up letters sent (37)
- Final set of questionnaires returned to surveyor (50)